At the Sept. 30 meeting of Weston's Zoning Board of Appeals, Town Manager Leon Gaumond spoke from his own experience. "As a town employee who happens to be in town center for pretty much 40 hours a week, I can assure you that the number of available spots in town center is plentiful," he told the board, according to the Weston Observer. The board then voted unanimously to approve a parking variance and also signed off on a special permit for restaurant use at the Josiah Smith Tavern. That cleared the way, on paper, for The Woods to move into the building on the Town Green.
For years, the question was whether a 1757 building could legally hold a modern restaurant. As of this month, the answer is yes. What remains is a building permit, a revised lease, and a race against the season.
A building that took fifteen years to say yes
Restaurateur Brian Piccini, a Weston resident since 2018, has put the timeline plainly. "The town has been working for 15 years before me to get this done," he told the Weston Observer in September 2025.
That history has a clear sequence:
- 2007: The tavern's exterior rehabilitation is completed, and the town begins looking for a new use for the tavern and the old library.
- 2009: A restaurant plan surfaces with 125 restaurant seats, a 75-seat function room, and an estimated $7.5 million project cost, as reported by the MetroWest Daily News. A special Town Meeting rejects restoration funding that same year.
- 2016: The Friends of the Josiah Smith Tavern become the town's preferred custodian. Their reuse plan puts a restaurant in the barn and connector, with nonprofit and event uses elsewhere in the building.
- 2019: Residents approve more than $12 million for further restoration.
- 2023: The town describes the restored tavern as code-compliant and ready for restaurant and nonprofit tenants, and Piccini's bid is accepted.
- March 2024: The Massachusetts Alcoholic Beverages Control Commission awards the restaurant's liquor license, and the Weston Historical Society approves the building plans.
Two constraints have followed the project the whole way. The town owns the tavern, but Historic New England holds a preservation deed restriction on it, so changes require that organization's input. The Weston Observer reported in December 2025 that the deed is between Historic New England and the town, not the restaurant tenant. The second constraint is the site itself. The tavern sits on the lot where it was built before the Revolution, and the lot has no room to add parking.
The parking problem, in numbers
This fall's approval came down to a gap that no amount of design work could close. According to the Weston Observer's Oct. 7 report, town bylaws require 77 parking spaces for the restaurant's 175-person capacity.
| Parking source | Spaces |
|---|---|
| Required by bylaw for 175-person capacity | 77 |
| On-site lot | 43 |
| On-street spaces approved earlier | 12 |
| Shortfall before the Sept. 30 variance | 22 |
Luke Legere, counsel for BU West LLC, the entity behind the restaurant, told the board that on-street parking was the only feasible option. "Essentially, it would render it impossible for the restaurant to be able to operate," he said. "The property and the tavern are both uniquely constrained due to their shape and configuration and location, all of which really stems from the fact they were established and constructed back in 1757."
The variance lets the restaurant count street parking toward the town's minimum. Board chair Stephen Larocque supported it but asked whether parking would become an issue during large events on the Green, including graduation. Board member Laura Mintz answered that a Town Green event could draw people who then go on to dinner, using the same space for both. "I don't think there's a way to fully resolve this," she said. "Without sufficient parking, this is a doomed situation." Rev. Jeffrey Barz-Snell of First Parish Church in Weston and Rev. Scott Euvrard of St. Julia Parish both wrote letters supporting the street-parking proposal. The Select Board had already approved the variance in June.
This vote resolved the question that stalled the project in the spring. On March 24, the ZBA recommended that Piccini withdraw his application without prejudice and refile. At the time, it was unclear who needed to sign off on street parking, and the Board of Health had not yet approved the septic system. That March report described a 189-seat plan, 49 of them outdoors, so the capacity figures in local coverage have changed as the plan has moved through review.
What still stands between the Green and a dinner reservation
With zoning settled, three items remain, according to the Oct. 7 report:
- A building permit. One still has to be submitted and approved before construction can begin.
- An amended sublease. In June, the Select Board gave the Friends a deadline for updated documents and timelines. In response, the Friends and Piccini asked the town to amend the sublease, and that contract is still under discussion. The Select Board has met in executive session about the tavern five times since early June. Gaumond said he expected town counsel to send something to the Friends in the coming days.
- A sign. The Woods has to return to the ZBA for approval of a proposed wooden blade sign. Friends president Jay Valenta said he did not expect that step to delay the project.
The weather sits on top of all three. "We're still on track, with the significant caveat that the window is closing here to get construction starting this fall," Valenta said. George Hanson, the Friends' vice president and treasurer, called the ZBA approvals "major, major breakthroughs."
How the opening date has moved
Each target opening date has been a reasonable forecast when it was made. Read in sequence, they also show how each new review step has pushed the date back.
| When it was reported | Target opening | Source |
|---|---|---|
| September 2025 | Spring 2026 | Weston Observer |
| December 2025 | Fall 2026 | Weston Observer |
| September 2026 | March 2027 | Weston Observer |
| October 2026 | "This spring," per the Friends | Weston Observer |
The March 2027 date came after Piccini's team met the Select Board's July 6 deadline for construction documents, proof of financial security, cost estimates, a business plan, and a permit memo. Board members called his July 14 update satisfactory. Spring 2027 remains a forecast, and it now depends on whether crews can start before the ground and the weather turn.
What the tavern is being fitted out to become
The plans explain why the fall construction start matters. Very little of the work shows from Boston Post Road. Piccini told the Observer that exterior changes would be limited to a small sign over the front door and a stone sign at the parking lot. Hoods, compressors, refrigeration, and emergency generators are to be kept out of sight from the road and walkways. Most of the work is inside the building.
As described in the September 2025 coverage:
- A wood-fired grill as the defining feature of the kitchen, with a family-friendly menu Piccini described as "very New England," built around farm-to-table and sea-to-table cooking, along with steaks and chicken.
- A 33-seat patio overlooking the Town Green, and a 16-seat courtyard between the inn and the barn under a wooden trellis or canvas cover.
- Three private dining rooms. These include a 45-seat room that was once the tavern's ballroom and one with the historic bar where, Piccini said, George Washington once stopped for a drink. When no private event is booked, those rooms can be set with two-tops and four-tops for regular dinner service.
- Craft cocktails and mocktails made with locally sourced honey and herbs from raised beds on site.
The Boston Globe's 2024 profile reported plans to source seafood from Captain Marden's and vegetables from Land's Sake Farm, with Boston Chops culinary director Corey Carter overseeing the menu. Piccini's Boston Urban Hospitality group also runs dbar in Dorchester, Deuxave in Back Bay, and Boston Chops in the South End and Downtown Crossing. The Woods would be its fifth restaurant.
At the Sept. 30 meeting, Piccini laid out the planned hours. Lunch would run from 11 a.m. to 3 p.m. and dinner from 4 p.m. to 9 p.m. Monday through Thursday, with later hours on Friday and Saturday and brunch from 10 a.m. on Sundays. That is a fuller schedule than the dinner-first launch the Globe described in 2024.
The next dates to watch
The sublease document from town counsel and a building-permit filing are the next concrete signs of progress. Either one would be reported in the Weston Observer, which has covered every step since 2025. The Friends' spring target depends on construction starting before winter.
Until then, the restaurant's planned produce supplier is the place to go this month. Land's Sake holds its free Halloween Fall Farm Fest on Saturday, Oct. 24, from 10 a.m. to 2 p.m. at 90 Wellesley St., with live music, farm animals, pumpkins, and a beer garden that is new this year.
A restaurant on the Town Green would change how Weston Town Center gets used in the evenings. Rachel Lieberman follows Weston's Town Center projects closely. If you would like to talk through how they could affect a move to or from the area around the Green, schedule a strategy call.